Mixed Use / Multifamily Projects

Ladd Tower

Ladd Tower is a 23 story glass tower located in downtown Portland’s south park blocks.  Ladd Tower features 332 apartments above ground floor retail and a sub grade parking structure.

American Heating installed all the wet-side and dry-side mechanical components for this project.  337 vertical fan coils, 1 450-ton chiller, hydronic piping, fans and all ductwork were all installed as part of our scope.

We also performed the HVAC services for the First Christian Church Restoration, also located on the Ladd block.

Categories
Civic / Cultural Projects

Resource Access Center

Resource Access Center is an 8-story facility located in the heart of downtown Portland.  Built for the Housing Authority of Portland, the RAC will provide a day center to help transition people out of homelessness, a 90 bed 24 hour shelter, and five floors of permanent housing with 130 studio apartments.

American Heating installed all the wet-side hydronics and dry-side mechanical components for this project. Six large custom air handlers were installed to condition the building.  Condensing boilers and heat recovery technology was also used to ensure building energy efficiency.

A state of the art Trane building management system was also installed by AHI to serve the building.

 

 

Categories
Education Projects

Gilbert Hall

Gilbert Hall located on Pacific University’s campus is a residence hall that houses 157 students.  Recognizing the value in VRF technology, Pacific University chose this option over several others.  Gilbert Hall is one of five LEED certified buildings on campus.

American Heating installed all components for the City Multi VRF system.  The installation included (8) outdoor condensers, (55) indoor fan coils and (8) BC controllers.  Mitsubishi’s control system manages the many zones within the building.

Mitsubishi posted a case study on their website too.

 

 

Categories
Projects Sports / Recreation

PGE Park (Jeld Wen Field)

PGE park was extensively renovated to prepare the stadium for Portland’s new major league soccer team. The renovations included the addition of a sit-down restaurant, remodeled locker rooms, renovated press boxes and the Providence rehabilitation clinic.

A Mitsubishi City-Multi system was installed to serve the new eastside grandstand and the Providence rehab clinic.

American Heating also performed the tenant improvement of the Providence Rehabilitation Clinic.

Categories
Featured Projects Retail / Grocery

New Seasons Markets

New Seasons is a locally-owned organic food market with 10 locations in Oregon. New Seasons’ customer-friendly designs have allowed them to adapt to urban environments and create a centerpiece of local neighborhoods.

American Heating, Inc. served as the design / build contractor on six of the 10 stores. We also installed the mechanical system on three stores that were designed by Interface Engineering.

New Seasons Markets strives to be environmentally conscious and sustainable. Through the use of highly efficient mechanical systems, these markets use less energy and have a drastically reduced carbon footprint.

***New Seasons 11th store located at Progress Ridge in Beaverton, OR is currently in the design phase. This will be the 10th store that American Heating has proudly been involved with.***

Link to PDF printable case study.

Categories
Education Projects

Fields & Schoenfeldt Hall

Fields & Schoenfeldt residence hall is located in Portland, Oregon on the University of Portland campus. The four-floor residence hall has space to house 318 students. It was the first residence hall on the campus to achieve LEED Gold status.

American Heating installed the Mitsubishi City Multi VRF system for this project which includes (15) outdoor heat pumps and (160) indoor fan coils. We also installed all of the refrigerant piping, performed start-up on all the HVAC equipment and installed the City Multi Control System.

 

Categories
Office Projects

Les Schwab Corporate HQ

Les Schwab relocated their corporate headquarters to Bend, OR in 2008. Their new 123,000 sf building houses offices, conference rooms, kitchens, locker rooms and a data center. Many energy conservation features were incorporated into the design.

Les Schwab contracted with American Heating to perform the mechanical install for this building. This enormous building is served by ten rooftop A/C units feeding an underfloor air distribution system that maximizes employee comfort. Two CRAC units and a roof mounted dry cooler handle the sizeable cooling load of the data center.

American Heating also installed a start-of-the-art Trane DDC system to serve this project. The Trane system provides building control through a single integrated interface allowing total control of the building’s indoor environment.

View full project details for the Les Schwab HQ heating and cooling system installation by downloading the PDF.

See the case study on Oregon Energy Trust website.

Categories
Featured Healthcare Projects

Providence Fishers Landing

American Heating served as the design/build contractor on this 15,000 square foot medical office building located in east Vancouver. Scheduled for completion in 2011, this building will provide various services to the community.

Utilizing a variable air volume system, this building will provide zoning capabilities ensuring optimum comfort level for all occupants.

Categories
High Tech Projects

Intel

American Heating has been involved with many projects at Intel.

Categories
Civic / Cultural Featured Projects

Mercy Corps

Located in downtown Portland’s Old Town district, the Mercy Corps project consisted of renovating 40,000 sf of the existing Packard Scott Building and an addition of 42,000 sf.

American Heating installed the Mitsubishi City Multi VRF system for this project which includes (13) outdoor heat pumps and (61) indoor fan coils. American Heating also programmed and installed the Mitsubishi control system to serve the building.

Three highly efficient Aaon packaged heat recovery units were also installed on the roof to serve the building. Nearly 8,000 feet of refrigerant piping was installed.

Check the Mercy Corps project breakdown on Mitsubishi’s website.